Bypass log audit BY-07: the temporary that became infrastructure

Force-permit entries, expiry voids, and unsigned restores decide whether interlocks still mean safety—plant safeguard audit, not near-miss permit forms, not SIS digitization decks, not OT inventory discovery logs.

Bypass log audit BY-07: the temporary that became infrastructure

Audit: BY-07 · Interlock / permissive bypass log
Window: 90 days
Finding class: Temporary bypasses without restore proof
Format: Log audit. Not a policy PDF.


Extract (anonymized rows)

| When | Tag / permissive | Reason | Expiry | Restore signed? | | --- | --- | --- | --- | --- | | D−88 | LAHH-221 force | “transmitter noisy” | blank | No | | D−61 | XV-19 open permissive | packing change | “this week” | No | | D−40 | ESD trip bypass | false trip hunt | blank | No | | D−12 | Same LAHH-221 | “still noisy” | blank | No | | D−3 | Batch complete bit force | MES lag | shift end | No |

Pattern: blank expiry + verbal week = permanent.

Bypass log binder open on an engineering desk

If expiry is blank, the bypass is already infrastructure.


Walkdown correlation

LAHH-221 still forced. Field transmitter dirty, not replaced. Operations learned to run with the force. New hires never saw the real trip.

XV-19 permissive still active three turnarounds later. “Packing change” completed on D−60.


Audit rules written in red

  1. No bypass without numeric expiry (datetime).
  2. Expiry auto-escalates to shift manager if unrestored.
  3. Same tag twice in 90 days → defect + MoC, not another force.
  4. MES / batch forces treated as safety-adjacent if they hide incomplete states.
  5. Photo of restored wiring / de-forced HMI required to close the row.

HMI showing a forced alarm with yellow force icon

A yellow force icon is not a maintenance plan.


Counts

  • Open bypasses at audit: 11
  • Past “this week” language: 7
  • Same-tag repeats: 4
  • Restore signatures on file: 2

Adjacent fences

Near-miss permit forms own job authorization theater. SIS lifecycle owns proof tests. Passive OT inventory owns asset naming. BY-07 owns bypass hygiene as a living log. Do not digitize the binder and keep blank expiries.


Close

Temporary is a timer. Without a timer, the plant has redesigned itself in the log—and called it operations.