On 28 September 2026 the U.S. Nuclear Regulatory Commission issued Construction Permit No. CPAR-2 to the Tennessee Valley Authority for Clinch River Nuclear Unit 1 in Roane County, Tennessee. The Federal Register notice followed on 5 October. GE Vernova Hitachi Nuclear Energy welcomed the decision the day after issuance. It is the first U.S. construction permit for a BWRX-300. It is not an operating license, and TVA has not announced a construction start.
The reactor is a 300 MW boiling-water small modular design from GE Vernova Hitachi. TVA filed the construction permit application in April 2025 on top of an existing early site permit (ESP-006) for Clinch River, near Oak Ridge National Laboratory. The permit is immediately effective. It sets the earliest completion of construction at 1 October 2031 and the latest at 30 September 2032. Those dates bound when the authorized construction must finish; they are not a public groundbreaking calendar.

North American BWRX-300 licensing is no longer a single project. Ontario Power Generation received a Canadian License to Construct for Darlington in April 2025 and has construction underway; its License to Operate application for the first unit was submitted in March 2026. Blue Energy filed the first part of a U.S. construction permit application in September 2026 for a Texas gas-plus-nuclear project using the same design family. Clinch River’s milestone is therefore a U.S. Part 50 construction authorization for TVA’s unit—not a fleet that is already pouring concrete in Tennessee.
Earlier coverage of Dow’s Long Mott Xe-100 case stopped at a finished staff safety evaluation without a permit. Clinch River crossed that line. Treating the permit as if fuel were loaded, or as if the latest completion date were a commercial online date, would still be wrong. The next documents that matter are TVA’s construction schedule, any cost-sharing arrangements the utility says it is still negotiating, and the operating-license application that comes after the plant is built.