Ørsted finishes building the 300 MW Hornsea 3 co-located battery

Q3 updates confirm construction of the 600 MWh Tesla Megapack system beside the Hornsea 3 onshore converter station is complete and that testing has begun—energisation and COD still ahead.

Cover · Energy

By Haluk Kilincer ·

← All analysis

Ørsted’s Q3 2026 construction update states that the 300 MW battery energy storage system co-located with the Hornsea 3 onshore converter station near Norwich is built and moving into testing. The system—publicly branded Iceni in project reporting—holds 600 MWh, using Tesla Megapack units on the same Norfolk land as the converter station. The 2024 final investment decision already fixed that rating and co-location choice; the new fact is construction complete, not commercial operation.

Trade and project coverage around the same milestone describe roughly 170 Megapacks in place, a split yard layout bridged by eighteen 33 kV cables each more than 600 m long, and a shared National Grid connection with Hornsea 3 that adds complexity versus a stand-alone BESS bay. Partners named in that reporting include Hitachi Energy, Knights Brown, and Tesla alongside Ørsted. Investor materials have carried BESS COD windows that moved with the wider Hornsea 3 schedule; treat those as planning dates, not a declared commercial start in the construction-complete note.

Battery containers flanking a converter-station compound

Construction complete plus testing start is not COD, not a published first-export hour, and not proof the shared Hornsea 3 connection is already exporting battery MWh under commercial contracts. The solid line in the update is hardware on the ground at rated 300 MW / 600 MWh beside the converter station, with Megapack gear and a testing campaign now under way.