Statkraft completed commissioning of phase one at Neilston Greener Grid Park near Paisley, Scotland, announcing the milestone on 12–13 November. The 50 MW battery energy storage system is the company’s first grid-forming BESS and, in Statkraft’s wording, one of the first such projects to enter commercial operation in the UK. Grid-forming inverters are described as able to support network voltage and frequency during disturbances—services historically tied to rotating machines—while batteries can also bid frequency response, voltage control, and balancing.
Construction of the first phase began in August 2023 after April 2022 consent. The wider site holds Scottish consent for up to 750 MW of BESS; that approval is separate from the 50 MW now in service, and Statkraft has not published an expansion timetable in these releases. The company places Neilston inside more than £2 billion of UK renewable infrastructure investment since 2006 and notes voluntary community funds already exceeding £50,000 near the site. Further UK stability work under construction includes a second grid-forming BESS at Coylton and synchronous compensators at Swansea and Necton.

Commercial operation of 50 MW is not the 750 MW consented envelope, not a published MWh duration, and not a full schedule of contracted stability services. Keep the operating phase at 50 MW, the grid-forming claim as Statkraft’s product description, and the larger consent as optionality still awaiting delivery decisions.